Phases 5 - 6

Click a section of the intersection to view the information on the various stages of the project.

Phase 5

Status: Completed

Duration: September 2019 thru October 2020

Location: SR 141 from Airport Road to Newport, Southbound I-95

Closures/Restrictions: Temporary signals on SR 141 at on-ramps

Progress Photos

Phase 5A

Status: Completed

Duration: September 2019 thru October 2019

Location: Ramp H (ramp from southbound SR 141 onto southbound I-95), Ramp K (ramp from southbound I-95 onto southbound SR 141)

Closures/Restrictions: Ramps closed

View Detour Map

Progress Photos

Phase 5B

Status: Completed

Duration: November 2019 thru December 2019

Location: Ramp L (ramp from northbound SR 141 onto southbound I-95), Ramp M (ramp from southbound I-95 to northbound SR 141)

Closures/Restrictions: Ramps closed

View Detour Map

Phase 5C

Status: Completed

Duration: Weekends thru September and October 2020

Location: Ramp G (Southbound SR 141 ramp onto northbound I-95)

View Closures/Restrictions

View Detour Map

Phase 5D

Status: Completed

Duration: Weekends thru November 2020 to July 2021

Location: SB SR 141 from Newport to Ramp H (Ramp from southbound SR 141 to southbound I-95), NB SR 141 from Ramp L (ramp from northbound SR 141 to southbound I-95 ramp) to Newport

View Detour Map

View Closure and Detour Info

Phase 5 Strip

Status: Completed

Duration: April 1, 2020 to April 15, 2020

Location: Southbound SR 141 from I-95 to Newport

View Closure and Detour Info

Phase 6

Status: Completed

Duration: October 2020 thru December 2021

Location: SR 141 from Airport Road to Newport, Southbound I-95

Closures/Restrictions: Temporary signal on Ramp K (southbound I95 ramp onto southbound SR 141)

View Detour Map

Phase 6 – Bridge Construction

Status: Completed

Duration: October 2020 thru December 2021

Location: SR 141 over southbound I-95

Closures/Restrictions: Occasional southbound I-95 lane and ramp closures

View Detour Map - Plan A

View Detour Map - Plan R

View Detour Map - Plan S

Phase 5 – Bridge Construction

Status: Completed

Duration: December 2019 thru October 2020

Location: SR 141 over southbound I-95

Closures/Restrictions: Occasional southbound I-95 lane and ramp closures

View Detour Map - Plan A

View Detour Map - Plan R

View Detour Map - Plan S

Phase 6A

Status: Completed

Duration: October 2020 to December 2020

Location: Ramp N (ramp from southbound I-295 onto northbound SR 141)

View Closure and Detour Info

View Detour Map